Selve optimizes engine production

In het kader van het project SELVE Totaal heeft SELVE zijn complete motorproductie opnieuw georganiseerd. “Dat proces is eind 2021 afgerond, zonder dat de productie is onderbroken of de klanten er iets van hebben gemerkt”, aldus projectleider Marc Solzbacher, verantwoordelijk voor productieverbetering en Lean Management gaat.
Under selve total
As part of the SELVE Total project, SELVE has reorganized its entire engine production. "That process was completed by the end of 2021, with no interruption in production or any impact on customers," said project leader Marc Solzbacher, who is responsible for production improvement and Lean Management. "Our production capacity is now 30% higher and our flexibility greater."

SELVE Total includes the four subprojects Administration, Production, File Management and Logistics. The Production subproject is the most advanced. Evidence of this is the optimized engine production. SELVE started Lean Production more than ten years ago. SELVE now produces more engines in more variants than ever. Engine production has been reorganized to respond adequately to future developments.
Holistic work process
As part of SELVE Total, Solzbacher is keeping an eye on the entire production and delivery process in order to respond to ever-increasing customer requirements. "With the complete conversion of our engine production, we are laying an important foundation for the overall project. On that basis, we are further building our holistic work process and implementing the Lean idea in all customer-relevant processes."
The redesign of engine production has been quite a tour de force, according to Solzbacher, especially since production has not been interrupted for it. "Production has been completely redesigned and 700,000 euros have been invested in new machinery. As a result, both production capacity - with 30% - and flexibility have been increased.
Flexible production lines
Engine production according to SELVE Total has been operating at full capacity since the end of 2021. SELVE claims that the production time of an engine has been halved. This has been achieved through a new LineDesign and a new layout of the production hall. Four production lines with eight test locations have been realized, in a smaller area than before. Production and test cycles were analyzed precisely per engine variant and per production line in order to achieve an optimal production sequence and to plan production even better in the future. Through Shopfloor Boards, the status of production can be constantly monitored and it becomes clear where priorities lie.
By streamlining production, SELVE has created space for a workstation for additional production or the manufacture of special drives. "The ongoing challenge is that we have to grow while making numerous changes," Solzbacher said. "One of the next steps is that by the middle of this year, the delivery of finished products should be optimized and adapted to customers' changing requirements and processes. The other sub-projects of SELVE Total should be in line with these developments in order to serve SELVE's customers even better in the future."